Approval for Network Rail to renew the signalling system for the Cambridge area.



Documents

Network Rail (Cambridge re-signalling) order decision


Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email webmasterdft@dft.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Network Rail (Cambridge re-signalling) order inspector’s report


Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email webmasterdft@dft.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Network Rail (Cambridge re-signalling) order application

Details

The Secretary of State for Transport’s decision to approve the application by Network Rail under the Transport and Works Act to compulsorily acquire land, and rights in land, and take temporary possession in connection with the works required for the re-signalling of the Cambridge Station interlocking area and the upgrade of the relevant level crossings

Application details

This application is made under the Transport and Works Act 1992.

  • order: The Network Rail (Cambridge re-signalling) Order

  • application status: decision issued

  • date of application: 5 August 2022

  • applicant: Network Rail via Addleshaw Goddard LLP